26 HILL STREET W1

MAJOR REFURBISHMENT OF FIVE STOREY GRADE II LISTED

RESIDENTIAL GEORGIAN TOWN HOUSE NEAR BERKELEY SQUARE

 

 

COMPLETED | 2018

INITIAL CONTRACT CONSTRUCTION VALUE | £ 2.73 MILLION

COMPLETION CONTRACT CONSTRUCTION VALUE | £ 1.61 MILLION

 

 

BUILDING OWNER | BERKELEY SQUARE HOLDINGS

GBSL CLIENT | ADP

PROJECT MANAGEMENT | ASTREA ASSET MANAGEMENT

PLANNING + LISTED BUILDING CONSENT | ROLFE JUDD PLANNING
ARCHITECTURE | GEOFF BROWN STUDIO FOR ADP

CONTRACT ADMINISTRATION | GEOFF BROWN STUDIO FOR ADP

STRUCTURAL ENGINEERING | HURST PEIRCE + MALCOLM

BUILDING SERVICES | PETER DEER AND ASSOCIATES

ACOUSTIC CONSULTANCY | PACE CONSULT

COST CONSULTANCY | CAPITA

CDM ADVISER | JACKSON COLES

FURNISHINGS | LUCARNA

INITIAL CONTRACTOR | LINK 2 BUILD

COMPLETION CONTRACTOR | KIND AND COMPANY [BUILDERS]

 

 

GEOFF BROWN STUDIO TEAM:

GEOFF BROWN | IZA GAJNY | ANNA BOROWSKA | SCOTT DOUCH |

GIORGIO ANDREINI | ANDRE LOBAO

 

PROJECT DESCRIPTION:

A DIFFICULT PROJECT CARRIED OUT UNDER TWO CONSTRUCTION

CONTRACTS AS THE FIRST CONTRACTOR CEASED TRADING WITH

ABOUT A THIRD OF THE WORKS STILL TO BE COMPLETED ON SITE.

THIS GRADE II LISTED PROPERTY HAD BEEN VACANT FOR 15 YEARS 

BEFORE REFURBISHMENT WORKS COMMENCED IN 2015 AND WAS IN A PARLOUS CONDITION WITH MULTIPLE DRY ROT FRUITING BODIES IN THE STAIR CORE AND ADJOINING ROOMS WHERE WATER 

PENETRATION HAD BEEN ONGOING FOR YEARS.

THE PROJECT INVOLVED COMPLETE REFURBISHMENT AND 

RESTORATION INSIDE AND OUT INCLUDING:

  • DEMOLITION OF THE ORIGINAL REAR EXTENSIONS AND REPLACEMENT WITH A NEW REAR BASEMENT LEVEL MEDIA ROOM AND GARDEN TERRACE ABOVE INCLUDING WALK-ON ROOFLIGHT

  • A MEDIA ROOM DESIGNED AS AN ACOUSTICALLY 
    INSULATED ‘BOX-IN-BOX’ STRUCTURE TO MITIGATE NOISE FROM THE JUBILEE UNDERGROUND LINE BELOW

  • NEW BESPOKE LIFT INSTALLATION WITH GLASS SHAFT
    INSERTED WITHIN THE STAIRWELL

  • REMOVAL OF 1950’S MOCK GEORGIAN PANELLING TO REVEAL GENUINE PERIOD PANELLING UNDERNEATH

  • REMOVAL OF DECORATIVE PARQUET FLOORING TO THE FIRST FLOOR PRINCIPAL ROOMS TO ALLOW ACCESS TO FLOOR VOIDS AND REPLACEMENT WITH NEW REPLICA PARQUET FLOORS BY WELDON

  • FIVE BEDROOMS ALL WITH NEW ENSUITE BATHROOMS

  • TWO KITCHENS

  • COMFORT COOLING TO LIVING SPACES AND THE MASTER
    BEDROOM SUITE

​